Contribuito alla realizzazione di “oggidomani” (tutto nello stesso anno):

Generalcontructor and timber construction 
Exetution planing: January/March
Production timber contruction: April (2 weeks)
Assambly timber contruction: Max/June (shell one store/day)

Basement, concret construction development
April

Windows, exterior door, shading
May (1 week)

Tinsmith roofer
May/June (2 weeks)

Plaster fasade
May/June (3 weeks)

Dry walls
May/July (5 weeks)

Electro / PV / power- and media distributor / unit
fire protection alarm and intercom system
May/July (4 weeks)

Hause technic
May/July (5 weeks)

With the latest technology from

The new heat pump a²X9, an integral total solution (heating, ventilation, hot water and coolin), optimized for highly eddicient buildings. Flexible, modular comtination options for many application variants.

Screed
June (2 weeks)

Locksmith


Tilex, painter, floors, doors
July/September

Tiling
company Robert Gieber

Carpentry 

and company Markus Oberrauner

Glacing 

Facilities
 October-December 

Logo and advertising material design

Insurance