Contributed to the impletation of “heutemorgen” (all in the same year):

Generalcontructor and timber construction 
Exetution planing: January/March
Production timber contruction: April (2 weeks)
Assambly timber contruction: Max/June (shell one store/day)

…

Basement, concret construction development
April

…

Windows, exterior door, shading
May (1 week)

…

Tinsmith roofer
May/June (2 weeks)

…

Plaster fasade
May/June (3 weeks)

…

Dry walls
May/July (5 weeks)

…

Electro / PV / power- and media distributor / unit
fire protection alarm and intercom system
May/July (4 weeks)

…

Hause technic
May/July (5 weeks)

With the latest technology from

The new heat pump a²X9, an integral total solution (heating, ventilation, hot water and coolin), optimized for highly eddicient buildings. Flexible, modular comtination options for many application variants.

…

Screed
June (2 weeks)

…

Locksmith


…

Tilex, painter, floors, doors
July/September

…
Tiling
company Robert Gieber

…

Carpentry 

and company Markus Oberrauner

…

Glacing 

…

Facilities
 October-December 

…

Logo and advertising material design

…
Insurance